Y様邸の進捗状況です。
外部では屋根板金工事がもう少しで完了します。
外壁材の搬入が完了し、水切り金物の取り付けが完了しています。
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2487-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2488-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2489-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2490-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2492-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2493-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2494-1024x768.jpg)
内部では壁断熱材工事、電気先行配線、ガス・水道の設備配管が完了しました。
現在は天井下地工事とフローリング貼り工事を進めています。
この後は天井断熱工事をしてから石膏ボード貼り工事へと進んでいきます。
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2496-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2499-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2500-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2501-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2502-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2503-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2504-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2505-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2506-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2507-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2508-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2509-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2510-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2511-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2512-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2513-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2514-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2515-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2516-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2517-1024x768.jpg)
![](https://build.mackenzie.co.jp/architecture/wp-content/uploads/2023/07/DSCN2518-1024x768.jpg)
Y様邸の進捗状況です。
外部では屋根板金工事がもう少しで完了します。
外壁材の搬入が完了し、水切り金物の取り付けが完了しています。
内部では壁断熱材工事、電気先行配線、ガス・水道の設備配管が完了しました。
現在は天井下地工事とフローリング貼り工事を進めています。
この後は天井断熱工事をしてから石膏ボード貼り工事へと進んでいきます。